Innavik Hydroelectric Project in Inukjuak - Follow-up to Condition 13 of the August 23, 2019, certificate of authorization
ᓄᓇ ᓱᕐᕋᑕᐅᔪᖅ
ᓯᕗᒧᐊᕐᓂᖓᑕ ᐊᓪᓗᓂᖓ /
ᐅᓕᕐᓀᕈᑎᖓ
Questions and comments (french only)
ᐅᓕᕐᓀᕈᑎᖓ pdf 290 KBᐅᓕᕐᓀᕈᑎᖓ
Condition 13:
Prior to the end of construction of the hydroelectric power plant, the proponent shall submit for authorization the fish habitat and wetland loss compensation plans. The proponent shall include any consultation undertaken as well as any feedback received. For fish habitat and wetland loss compensation, the request for authorization shall specify any required work related to the project, including construction of access roads and/or infrastructure. Compensation plans shall also include monitoring of the planned measures. Compensation plans shall be implemented no later than two (2) years after the electric power plant has entered service.