Name of the project /

Strange Lake Rare Earth Mining Project

Strange Lake Rare Earth Mining Project
Proponent /
Torngat Metals ltd
Expected date of construction /
2026-2027
Community /
Lake Brisson
Location /
The Mining Project is situated near Brisson Lake, Nunavik, 235 km north-east of Schefferville, 325 km south of Kuujjuaq, 285 km south-east of Kangiqsualujjuaq and 237 km north-east of Kawawachikamach

Affected area

The Strange Lake alkaline complex occupies a total area of 3,600 ha, whereas Lake Brisson occupies a total surface area of 3,200 ha. Lake Brisson flows into Napeu Kainut Lake, and then into the Déat River. The primary hydrographic basin is that of the George River, which is located about 100 km downstream of the mine site considering the waterflow (the George River is approximately 30 kms due East of the mine site). The project site is located on category III Land.

Step of the procedure /

Project submission
Evaluation
Preparation of impact study
Review and public participation
Decision and authorization

Decision

Guidelines for the Environmental and Social Impacts Study

Decision pdf 267 KB

Description

The project mainly includes an open pit, a tailings management facility, a low-grade ore pile, a waste rock pile, a collection basin, an industrial area housing the ore mill and the camp, an airstrip and a landfill. The proponent also plans to develop a 160 km access road linking the mine to port facilities on the east coast of Labrador. An 18 km section of this road will be located in Quebec.
During the 30-year operation phase, between 160 and 200 million tonnes of ore will be extracted from the open pit, or an average of 5.7 to 6.7 million tonnes per year. Between 125,000 to 300,000 tonnes per year of rare earth concentrate will then be produced by on-site beneficiation plant with a processing capacity of 16,000 to 20,000 tonnes of crushed ore per day.

Calendar

see below

Additionnal informations

For more information, contact the KEQC secretariat.

Project Schedule submitted by the promoter

Submission of preliminary Environmental Impact Assessment information April 2023
Start of the final phase of the Pre-Feasibility Study August 2024
Issuance of the Pre-Feasibility Study (PFS) December 2024
Start of Feasibility Study (FS) January 2025
Submission of the Environmental Impact Assessment report May 2025
Feasibility Study completed May 2025
Environmental Impact Assessment decision (MELCCFP/Kativik) April 2026
Development and construction phases 2026-2027
Detailed engineering, applications for certificates of authorization, obtaining certificates and
construction work (in phases) 2026-2027
Beginning of mining operations and start of mining processing End of 2027
Operational phase (30-year operation) 2027-October 2057
Post-operation environmental monitoring (annual over 5 years) 2057-2062
Closure and restoration phase 2057-2062
Post-restoration environmental monitoring (annual monitoring) 2062-2072 (minimum
duration)