Name of the project /

Project of Development of a Borrow Pit for the Project of New Thermal Power Generating Station in Aupaluk

Project of Development of a Borrow Pit for the Project of New Thermal Power Generating Station in Aupaluk
Proponent /
CRT Construction
Expected date of construction /
2025
Community /
Aupaluk
Location /
The projected site is located east of the village

Affected area

The site is already partially de-capped, as it has previously housed a quarry or sandpit of approximately 2.3 ha; this project will expand the area by approximately 3.7 ha.

Step of the procedure /

Project submission
Evaluation
Preparation of impact study
Review and public participation
Decision and authorization

Decision

Guidelines for of the preparation of the environmental and social impact assessment (French only)

Decision pdf 153 KB

Description

The goal of this project is to extract the materials needed to lay the foundations for a new thermal power plant in Aupaluk, ensuring a reliable and sustainable energy source that will meet the community’s growing electricity needs. The proponent of this project was commissioned by Hydro-Québec to build the plant’s foundations. The projected site is located east of the village. The site is already partially de-capped, as it has previously housed a quarry or sandpit of approximately 2.3 ha; this project will expand the area by approximately 3.7 ha. The sandpit will produce approximately 28,000 m3 of backfill, and stripping and backfilling activities are planned.
Under Annex A of Title II of the Environmental Quality Act (EQA), any proposed borrow pit, sandpit or quarry project with an area to be stripped of 3 hectares or more is subject to the impact assessment process.